Planta y Fachada
| Costos de Construcción en Steel Frame | |||||
| Casa Unifamiliar “SpeedHome” de 84.5 m² | PRECIO por m² $1,299,848.64 | |||||
| Porcentaje de variabilidad con respecto al mes anterior 3.02% | |||||
| # | Descripción de Actividad | Materiales | Mano de Obra | Total Mat. + M.O. | % Rubro |
| 1 | Diseño de Obra, Proyecto de Ingeniería y Planos Técnicos de Obra | $0.00 | $6,447,444.24 | $6,447,444.24 | 5.87% |
| 2 | Trabajos Preliminares, dirección y gestión integral | $0.00 | $13,872,439.65 | $13,872,439.65 | 12.63% |
| 3 | Obra Civil (platea de HA, cañería cloacal y pluvial) | $6,928,888.19 | $1,803,170.02 | $8,732,058.21 | 7.95% |
| 4 | Estructura de acero | $13,656,965.40 | $2,555,006.82 | $16,211,972.22 | 14.76% |
| 5 | Diafragma de rigidización (OSB) | $2,909,170.32 | $759,392.50 | $3,668,562.82 | 3.34% |
| 6 | Techo de chapa y zinguería | $2,205,641.02 | $155,859.00 | $2,361,500.02 | 2.15% |
| 7 | Barrera de agua y viento/EPS 25mm x 30kg | $2,827,989.63 | $1,81,068.54 | $4,009,058.17 | 3.65% |
| 8 | Basecoat y malla de fibra de vidrio | $1,053,026.91 | $1,901,594.05 | $2,954,620.96 | 2.69% |
| 9 | Instalación de luz | $1,791,973.47 | $2,755,287.04 | $4,547,260.51 | 4.14% |
| 10 | Instalación de agua | $990,928.96 | $1,381,554.78 | $2,372,483.74 | 2.16% |
| 11 | Instalación de gas | $491,299.35 | $1,375,933.22 | $1,867,232.57 | 1.70% |
| 12 | Aislaciones (lana de vidrio de 100mm) | $5,403,990.74 | $0.00 | $5,403,990.74 | 4.92% |
| 13 | Emplacado Interior de cielo rasos y muros | $3,368,506.23 | $3,869,765.92 | $7,238,272.15 | 6.59% |
| 14 | Aberturas (modena blanco con vidrios 3+3) | $12,938,823.36 | $0.00 | $12,938,823.36 | 11.78% |
| 15 | Pintura Interior | $232,810.43 | $1,788,194.23 | $2,021,004.66 | 1.84% |
| 16 | Revestimiento plástico exterior | $870,977.30 | $919,369.23 | $1,790,346.53 | 1.63% |
| 17 | Pisos interiores, veredas y revestimientos de baño y cocina | $4,306,248.85 | $2,273,000.04 | $6,579,248.89 | 6.21% |
| 18 | Otros | $6,820,890.75 | $0.00 | $6,820,890.75 | 6.21% |
| Subtotales | $66,798,130.91 | $43,039,079.28 | $109,837,210.19 | 100.00% | |
| Participación % | 60.82% | 39.18% | |||
| Precio por M2 | $790,510.42 | $509,338.22 | $1,299,848.64 | ||
| *Sin Cochera y sin mueble de cocina.
*Los valores expresados son aproximados |
|||||
Planta y Fachada
*Imágenes ilustrativas.
| Costos de Construcción en Steel Frame | |||||
| Casa de Diseño de 206.4 M2 | PRECIO por m² $1,422,690.23 | |||||
| Porcentaje de variabilidad con respecto al mes anterior 3.02% | |||||
| # | Descripción de Actividad | Materiales | Mano de Obra | Total Mat. + M.O. | % Rubro |
| 1 | Diseño de Obra, Proyecto de Ingeniería y Planos Técnicos de Obra | $0.00 | $18,633,792.71 | $18,633,792.71 | 6.35% |
| 2 | Tareas preliminares (estudio de suelo, movimiento y compactación) | $0.00 | $41,408,428.15 | $41,408,428.15 | 14.10% |
| 3 | Obra Civil (platea de HA, cañería cloacal y pluvial) | $20,502,634.39 | $6,587,781.53 | $27,090,415.92 | 9.23% |
| 4 | Estructura de acero | $46,362,412.94 | $5,402,733.75 | $51,765,146.69 | 17.63% |
| 5 | Diafragma de rigidización (OSB) | $6,891,556.55 | $1,800,911.22 | $8,692,467.77 | 2.96% |
| 6 | Techo de chapa y zinguería | $11,085,866.84 | $600,303.74 | $11,686,170.58 | 3.98% |
| 7 | Barrera de agua y viento/EPS 25mm x 30kg | $6,011,719.18 | $1,320,668.29 | $7,332,387.47 | 2.50% |
| 8 | Basecoat y malla de fibra de vidrio | $5,225,926.08 | $2,881,457.97 | $8,107,384.05 | 2.76% |
| 9 | Instalación de luz | $7,224,874.70 | $6,274,004.33 | $13,498,879.02 | 4.60% |
| 10 | Instalación de agua | $1,927,206.09 | $3,137,002.08 | $5,064,208.18 | 1.72% |
| 11 | Instalación de gas | $1,148,144.83 | $3,137,002.08 | $4,285,146.92 | 1.46% |
| 12 | Aislaciones (lana de vidrio de 100mm) | $11,044,349.96 | $0.00 | $11,044,349.96 | 3.76% |
| 13 | Emplacado Interior de cielo rasos y muros | $11,908,145.32 | $7,414,248.68 | $19,322,393.99 | 6.58% |
| 14 | Aberturas (modena blanco con vidrios 3+3) | $26,351,126.29 | $0.00 | $26,351,126.29 | 8.97% |
| 15 | Pintura Interior | $527,298.90 | $3,633,489.52 | $4,160,788.42 | 1.42% |
| 16 | Revestimiento plástico exterior | $2,243,262.07 | $1,305,008.18 | $3,548,270.24 | 1.21% |
| 17 | Pisos interiores, veredas y revestimientos de baño y cocina | $15,907,181.65 | $4,940,836.17 | $20,848,017.82 | 7.10% |
| 18 | Otros | $5,401,944.58 | $5,401,944.58 | $10,803,889.16 | 3.68% |
| Subtotales | $179,763,650.35 | $113,879,612.99 | $293,643,263.34 | 100.00% | |
| Participación % | 61.22% | 38.78% | |||
| Precio por M2 | $870,947.92 | $551,742.31 | $1,422,690.23 | ||
| *Sin Cochera y sin mueble de cocina.
*Los valores expresados son aproximados |
|||||
Planta y Fachada
- Imagen ilustrativa
*Imágenes ilustrativas.
| Costos de Construcción en Steel Frame | |||||
| Town House de 115 M2 | PRECIO por m² $1,490,703.85 | |||||
| Porcentaje de variabilidad con respecto al mes anterior 3.02% | |||||
| # | Descripción de Actividad | Materiales | Mano de Obra | Total Mat. + M.O. | % Rubro |
| 1 | Proyecto, dirección, legales y gestión integral | $0.00 | $29,644,914.92 | $29,644,914.92 | 17.29% |
| 2 | Tareas preliminares (estudio de suelo, movimiento y compactación) | $0.00 | $1,274,746.29 | $1,274,746.29 | 0.74% |
| 3 | Obra Civil (platea de HA, cañería cloacal y pluvial) | $10,972,542.08 | $2,645,224.52 | $13,617,766.60 | 7.94% |
| 4 | Estructura de acero | $33,521,637.85 | $3,375,117.69 | $36,896,755.54 | 21.52% |
| 5 | Diafragma de rigidización (OSB) | $5,882,944.49 | $592,322.77 | $6,475,267.26 | 3.78% |
| 6 | Techo de chapa y zinguería | $5,376,736.12 | $541,355.34 | $5,918,091.46 | 3.45% |
| 7 | Barrera de agua y viento/EPS 25mm x 30kg | $3,483,828.08 | $350,768.38 | $2,942,324.88 | 2.24% |
| 8 | Basecoat y malla de fibra de vidrio | $2,673,176.73 | $269,148.15 | $7,710,012.32 | 1.72% |
| 9 | Instalación de luz | $5,239,602.69 | $2,470,409.63 | $2,363,643.68 | 4.50% |
| 10 | Instalación de agua | $1,274,381.50 | $1,089,262.18 | $2,103,575.91 | 1.38% |
| 11 | Instalación de gas | $1,134,163.43 | $969,412.48 | $7,539,686.46 | 1.23% |
| 12 | Aislaciones (lana de vidrio de 100mm) | $6,927,546.26 | $612,140.20 | $7,539,686.46 | 4.40% |
| 13 | Emplacado Interior de cielo rasos y muros | $7,944,682.48 | $2,448,560.86 | $10,393,243.34 | 6.06% |
| 14 | Aberturas (modena blanco con vidrios 3+3) | $18,116,336.95 | $0.00 | $18,116,336.95 | 10.57% |
| 15 | Pintura Interior | $392,099.26 | $1,524,707.44 | $1,916,806.70 | 1.12% |
| 16 | Revestimiento plástico exterior | $1,344,247.69 | $657,527.27 | $2,001,774.95 | 1.17% |
| 17 | Pisos interiores, veredas y revestimientos de baño y cocina | $11,619,251.167 | $1,983,918.42 | $13,603,170.08 | 7.94% |
| 18 | Otros | $5,078,228.49 | $0.00 | $5,078,228.49 | 2.96% |
| Subtotales | $117,619,251.67 | $50,449,536.54 | $171,430,942.28 | 100.00% | |
| Participación % | 70.57% | 29.43% | |||
| Precio por M2 | $1,052,012.22 | $438,691.62 | $1,490,703.85 | ||
| *Los valores expresados son aproximados | |||||
*Todas las imágenes son ilustrativas.