Planta y Fachada
| Costos de Construcción en Steel Frame | |||||
| Casa Unifamiliar “SpeedHome” de 84.5 m² | PRECIO por m² $1,261,750.05 | |||||
| Porcentaje de variabilidad con respecto al mes anterior 1.37% | |||||
| # | Descripción de Actividad | Materiales | Mano de Obra | Total Mat. + M.O. | % Rubro | 
| 1 | Diseño de Obra, Proyecto de Ingeniería y Planos Técnicos de Obra | $0.00 | $6,258,469.49 | $6,258,469.49 | 5.86% | 
| 2 | Trabajos Preliminares, dirección y gestión integral | $0.00 | $13,465,838.10 | $13,465,838.10 | 12.63% | 
| 3 | Obra Civil (platea de HA, cañería cloacal y pluvial) | $6,725,802.31 | $1,750,319.06 | $8,476,121.37 | 7.95% | 
| 4 | Estructura de acero | $13,256,679.41 | $2,480,119.51 | $15,736,798.92 | 14.76% | 
| 5 | Diafragma de rigidización (OSB) | $2,823,902.46 | $737,134.69 | $3,561,037.15 | 3.34% | 
| 6 | Techo de chapa y zinguería | $2,140,993.63 | $151,290.77 | $2,292,284.40 | 2.15% | 
| 7 | Barrera de agua y viento/EPS 25mm x 30kg | $2,745,101.19 | $1,146,451.39 | $3,891,552.58 | 3.65% | 
| 8 | Basecoat y malla de fibra de vidrio | $1,022,162.66 | $1,845,858.28 | $2,868,020.94 | 2.69% | 
| 9 | Instalación de luz | $1,739,450.68 | $2,674,529.51 | $4,413,980.19 | 4.14% | 
| 10 | Instalación de agua | $961,884.80 | $1,341,061.38 | $2,302,946.18 | 2.16% | 
| 11 | Instalación de gas | $476,899.36 | $1,335,604.58 | $1,812,503.94 | 1.70% | 
| 12 | Aislaciones (lana de vidrio de 100mm) | $5,245,599.64 | $0.00 | $5,245,599.64 | 4.92% | 
| 13 | Emplacado Interior de cielo rasos y muros | $3,269,775.23 | $3,756,342.99 | $7,026,118.22 | 6.59% | 
| 14 | Aberturas (modena blanco con vidrios 3+3) | $12,559,586.13 | $0.00 | $12,559,586.13 | 11.78% | 
| 15 | Pintura Interior | $225,986.76 | $1,735,782.22 | $1,961,768.98 | 1.84% | 
| 16 | Revestimiento plástico exterior | $845,448.93 | $892,422.50 | $1,737,871.43 | 1.63% | 
| 17 | Pisos interiores, veredas y revestimientos de baño y cocina | $4,180,032.59 | $2,206,378.36 | $6,386,410.95 | 5.99% | 
| 18 | Otros | $6,620,970.28 | $0.00 | $6,620,970.28 | 6.21% | 
| Subtotales | $64,840,276.06 | $41,777,602.83 | $106,617,878.89 | 100.00% | |
| Participación % | 60.82% | 39.18% | |||
| Precio por M2 | $767,340.55 | $494,409.50 | $1,261,750.05 | ||
| *Sin Cochera y sin mueble de cocina.
 *Los valores expresados son aproximados  | 
|||||
Planta y Fachada
*Imágenes ilustrativas.
| Costos de Construcción en Steel Frame | |||||
| Casa de Diseño de 206.4 M2 | PRECIO por m² $1,380,984.50 | |||||
| Porcentaje de variabilidad con respecto al mes anterior 1.37% | |||||
| # | Descripción de Actividad | Materiales | Mano de Obra | Total Mat. + M.O. | % Rubro | 
| 1 | Diseño de Obra, Proyecto de Ingeniería y Planos Técnicos de Obra | $0.00 | $18,087,548.74 | $18,087,548.74 | 6.35% | 
| 2 | Tareas preliminares (estudio de suelo, movimiento y compactación) | $0.00 | $40,194,552.66 | $40,194,552.66 | 14.10% | 
| 3 | Obra Civil (platea de HA, cañería cloacal y pluvial) | $19,901,605.89 | $6,394,662.72 | $26,296,268.61 | 9.23% | 
| 4 | Estructura de acero | $45,003,312.89 | $5,244,354.25 | $50,247,667.14 | 17.63% | 
| 5 | Diafragma de rigidización (OSB) | $6,689,532.66 | $1,748,118.06 | $8,437,650.72 | 2.96% | 
| 6 | Techo de chapa y zinguería | $10,760,888.02 | $582,706.02 | $11,343,594.04 | 3.98% | 
| 7 | Barrera de agua y viento/EPS 25mm x 30kg | $5,835,487.46 | $1,281,953.30 | $7,117,440.76 | 2.50% | 
| 8 | Basecoat y malla de fibra de vidrio | $5,072,729.64 | $2,796,988.91 | $7,869,718.55 | 2.76% | 
| 9 | Instalación de luz | $7,013,079.69 | $6,090,083.79 | $13,103,163.49 | 4.60% | 
| 10 | Instalación de agua | $1,870,710.63 | $3,045,041.82 | $4,915,752.45 | 1.72% | 
| 11 | Instalación de gas | $1,114,487.32 | $3,045,041.82 | $4,159,529.14 | 1.46% | 
| 12 | Aislaciones (lana de vidrio de 100mm) | $10,720,588.19 | $0.00 | $10,720,588.19 | 3.76% | 
| 13 | Emplacado Interior de cielo rasos y muros | $11,559,061.65 | $7,196,902.23 | $18,755,963.88 | 6.58% | 
| 14 | Aberturas (modena blanco con vidrios 3+3) | $25,578,651.03 | $0.00 | $25,578,651.03 | 8.97% | 
| 15 | Pintura Interior | $511,841.29 | $3,526,974.88 | $4,038,816.17 | 1.42% | 
| 16 | Revestimiento plástico exterior | $2,177,501.52 | $1,266,752.26 | $3,444,253.78 | 1.21% | 
| 17 | Pisos interiores, veredas y revestimientos de baño y cocina | $15,440,867.45 | $4,795,997.06 | $20,236,864.51 | 7.10% | 
| 18 | Otros | $5,243,588.22 | $5,243,588.22 | $10,487,176.43 | 3.68% | 
| Subtotales | $174,493,933.56 | $110,541,266.73 | $285,035,200.29 | 100.00% | |
| Participación % | 61.22% | 38.78% | |||
| Precio por M2 | $845,416.34 | $535,568.15 | $1,380,984.50 | ||
| *Sin Cochera y sin mueble de cocina.
 *Los valores expresados son aproximados  | 
|||||
Planta y Fachada
- Imagen ilustrativa
 
*Imágenes ilustrativas.
| Costos de Construcción en Steel Frame | |||||
| Town House de 115 M2 | PRECIO por m² $1,447,004.32 | |||||
| Porcentaje de variabilidad con respecto al mes anterior 1.37% | |||||
| # | Descripción de Actividad | Materiales | Mano de Obra | Total Mat. + M.O. | % Rubro | 
| 1 | Proyecto, dirección, legales y gestión integral | $0.00 | $28,775,883.24 | $28,775,883.24 | 17.29% | 
| 2 | Tareas preliminares (estudio de suelo, movimiento y compactación) | $0.00 | $1,237,377.49 | $1,237,377.49 | 0.74% | 
| 3 | Obra Civil (platea de HA, cañería cloacal y pluvial) | $10,650,885.34 | $2,567,680.57 | $13,218,565.91 | 7.94% | 
| 4 | Estructura de acero | $32,538,961.22 | $3,276,177.14 | $35,815,138.36 | 21.52% | 
| 5 | Diafragma de rigidización (OSB) | $5,710,487.76 | $574,959.01 | $6,285,446.77 | 3.78% | 
| 6 | Techo de chapa y zinguería | $5,219,118.73 | $525,485.67 | $5,744,604.40 | 3.45% | 
| 7 | Barrera de agua y viento/EPS 25mm x 30kg | $3,381,700.72 | $340,485.71 | $3,722,186.43 | 2.24% | 
| 8 | Basecoat y malla de fibra de vidrio | $2,594,813.36 | $261,258.15 | $2,856,071.52 | 1.72% | 
| 9 | Instalación de luz | $5,086,005.33 | $2,397,990.32 | $7,483,995.65 | 4.50% | 
| 10 | Instalación de agua | $1,237,023.39 | $1,057,330.79 | $2,294,354.19 | 1.38% | 
| 11 | Instalación de gas | $1,100,915.77 | $940,994.45 | $2,041,910.22 | 1.23% | 
| 12 | Aislaciones (lana de vidrio de 100mm) | $6,724,467.34 | $594,195.50 | $7,318,662.84 | 4.40% | 
| 13 | Emplacado Interior de cielo rasos y muros | $7,711,786.53 | $2,376,782.04 | $10,088,568.57 | 6.06% | 
| 14 | Aberturas (modena blanco con vidrios 3+3) | $17,585,262.03 | $0.00 | $17,585,262.03 | 10.57% | 
| 15 | Pintura Interior | $380,604.99 | $1,480,011.11 | $1,860,616.09 | 1.12% | 
| 16 | Revestimiento plástico exterior | $1,304,841.48 | $638,252.05 | $1,943,093.53 | 1.17% | 
| 17 | Pisos interiores, veredas y revestimientos de baño y cocina | $11,278,636.83 | $1,925,760.45 | $13,204,397.29 | 7.94% | 
| 18 | Otros | $4,929,361.76 | $0.00 | $4,929,361.76 | 2.96% | 
| Subtotales | $117,434,872.59 | $48,970,623.70 | $166,405,496.29 | 100.00% | |
| Participación % | 70.57% | 29.43% | |||
| Precio por M2 | $1,021,172.81 | $425,831.51 | $1,447,004.32 | ||
| *Los valores expresados son aproximados | |||||
*Todas las imágenes son ilustrativas.
					