Planta y Fachada
| Costos de Construcción en Steel Frame | |||||
| Casa Unifamiliar “SpeedHome” de 84.5 m² | PRECIO por m² $1,322,703.58 | |||||
| Porcentaje de variabilidad con respecto al mes anterior 1.76% | |||||
| # | Descripción de Actividad | Materiales | Mano de Obra | Total Mat. + M.O. | % Rubro |
| 1 | Diseño de Obra, Proyecto de Ingeniería y Planos Técnicos de Obra | $0.00 | $6,560,808.14 | $6,560,808.14 | 5.87% |
| 2 | Trabajos Preliminares, dirección y gestión integral | $0.00 | $14,116,355.51 | $14,116,355.51 | 12.63% |
| 3 | Obra Civil (platea de HA, cañería cloacal y pluvial) | $7,050,717.21 | $1,834,874.74 | $8,885,591.95 | 7.95% |
| 4 | Estructura de acero | $13,897,092.63 | $2,599,930.91 | $16,497,023.54 | 14.76% |
| 5 | Diafragma de rigidización (OSB) | $2,960,321.58 | $772,744.72 | $3,733,066.30 | 3.34% |
| 6 | Techo de chapa y zinguería | $2,244,422.29 | $158,599.43 | $2,403,021.72 | 2.15% |
| 7 | Barrera de agua y viento/EPS 25mm x 30kg | $2,877,713.52 | $1,201,834.99 | $4,079,548.51 | 3.65% |
| 8 | Basecoat y malla de fibra de vidrio | $1,071,542.03 | $1,935,029.33 | $3,006,571.36 | 2.69% |
| 9 | Instalación de luz | $1,823,481.32 | $2,803,732.60 | $4,627,213.92 | 4.14% |
| 10 | Instalación de agua | $1,008,352.23 | $1,405,846.34 | $2,414,198.57 | 2.16% |
| 11 | Instalación de gas | $499,007.85 | $1,400,125.93 | $1,900,063.68 | 1.70% |
| 12 | Aislaciones (lana de vidrio de 100mm) | $5,499,007.85 | $0.00 | $5,499,007.85 | 4.92% |
| 13 | Emplacado Interior de cielo rasos y muros | $3,427,733.89 | $3,937,807.11 | $7,365,541.00 | 6.59% |
| 14 | Aberturas (modena blanco con vidrios 3+3) | $13,166,323.67 | $0.00 | $13,166,323.67 | 11.78% |
| 15 | Pintura Interior | $236,903.89 | $1,819,635.63 | $2,056,539.52 | 1.84% |
| 16 | Revestimiento plástico exterior | $886,291.49 | $935,534.28 | $1,821,825.77 | 1.63% |
| 17 | Pisos interiores, veredas y revestimientos de baño y cocina | $4,381,964.62 | $2,312,965.67 | $6,694,930.29 | 6.21% |
| 18 | Otros | $6,940,820.88 | $0.00 | $6,940,820.88 | 6.21% |
| Subtotales | $67,972,626.85 | $43,795,825.33 | $111,768,452.18 | 100.00% | |
| Participación % | 60.82% | 39.18% | |||
| Precio por M2 | $804,409.79 | $518,293.79 | $1,322,703.58 | ||
|
*Sin Cochera y sin mueble de cocina. *Los valores expresados son aproximados |
|||||
Planta y Fachada
*Imágenes ilustrativas.
| Costos de Construcción en Steel Frame | |||||
| Casa de Diseño de 206.4 M2 | PRECIO por m² $1,447,729.58 | |||||
| Porcentaje de variabilidad con respecto al mes anterior 1.76% | |||||
| # | Descripción de Actividad | Materiales | Mano de Obra | Total Mat. + M.O. | % Rubro |
| 1 | Diseño de Obra, Proyecto de Ingeniería y Planos Técnicos de Obra | $0.00 | $18,961,747.46 | $18,961,747.46 | 6.35% |
| 2 | Tareas preliminares (estudio de suelo, movimiento y compactación) | $0.00 | $42,137,216.49 | $42,137,216.49 | 14.10% |
| 3 | Obra Civil (platea de HA, cañería cloacal y pluvial) | $20,863,480.75 | $6,703,726.49 | $27,567,207.24 | 9.23% |
| 4 | Estructura de acero | $47,178,391.40 | $5,497,821.86 | $52,676,213.27 | 17.63% |
| 5 | Diafragma de rigidización (OSB) | $7,012,847.95 | $1,832,607.26 | $8,845,455.21 | 2.96% |
| 6 | Techo de chapa y zinguería | $11,280,978.10 | $610,869.08 | $11,891,847.18 | 3.98% |
| 7 | Barrera de agua y viento/EPS 25mm x 30kg | $6,117,525.44 | $1,343,912.05 | $7,461,437.49 | 2.50% |
| 8 | Basecoat y malla de fibra de vidrio | $5,317,902.38 | $2,932,171.63 | $8,250,074.01 | 2.76% |
| 9 | Instalación de luz | $7,352,032.49 | $6,384,426.80 | $13,736,459.29 | 4.60% |
| 10 | Instalación de agua | $1,961,124.92 | $3,192,213.32 | $5,153,338.24 | 1.72% |
| 11 | Instalación de gas | $1,168,352.18 | $3,192,213.32 | $4,360,565.50 | 1.46% |
| 12 | Aislaciones (lana de vidrio de 100mm) | $11,238,730.52 | $0.00 | $11,238,730.52 | 3.76% |
| 13 | Emplacado Interior de cielo rasos y muros | $12,117,728.67 | $7,544,739.45 | $19,662,468.13 | 6.58% |
| 14 | Aberturas (modena blanco con vidrios 3+3) | $26,814,906.11 | $0.00 | $26,814,906.11 | 8.97% |
| 15 | Pintura Interior | $536,579.36 | $3,697,438.94 | $4,234,018.30 | 1.42% |
| 16 | Revestimiento plástico exterior | $2,282,743.48 | $1,327,976.32 | $3,610,719.80 | 1.21% |
| 17 | Pisos interiores, veredas y revestimientos de baño y cocina | $16,187,148.04 | $5,027,794.89 | $21,214,942.93 | 7.10% |
| 18 | Otros | $5,497,018.80 | $5,497,018.80 | $10,994,037.61 | 3.68% |
| Subtotales | $182,927,490.601 | $115,883,894.18 | $298,811,384.78 | 100.00% | |
| Participación % | 61.22% | 38.78% | |||
| Precio por M2 | $886,276.60 | $561,452.98 | $1,447,729.58 | ||
|
*Sin Cochera y sin mueble de cocina. *Los valores expresados son aproximados |
|||||
Planta y Fachada
- Imagen ilustrativa
*Imágenes ilustrativas.
| Costos de Construcción en Steel Frame | |||||
| Town House de 115 M2 | PRECIO por m² $1,516,940.23 | |||||
| Porcentaje de variabilidad con respecto al mes anterior 1.76% | |||||
| # | Descripción de Actividad | Materiales | Mano de Obra | Total Mat. + M.O. | % Rubro |
| 1 | Proyecto, dirección, legales y gestión integral | $0.00 | $30,166,665.42 | $30,166,665.42 | 17.29% |
| 2 | Tareas preliminares (estudio de suelo, movimiento y compactación) | $0.00 | $1,297,181.82 | $1,297,181.82 | 0.74% |
| 3 | Obra Civil (platea de HA, cañería cloacal y pluvial) | $11,165,658.82 | $2,691,780.47 | $13,857,439.29 | 7.94% |
| 4 | Estructura de acero | $34,111,618.68 | $3,434,519.76 | $37,546,138.43 | 21.52% |
| 5 | Diafragma de rigidización (OSB) | $5,986,484.31 | $602,747.65 | $6,589,231.97 | 3.78% |
| 6 | Techo de chapa y zinguería | $5,471,366.67 | $550,883.19 | $6,022,249.86 | 3.45% |
| 7 | Barrera de agua y viento/EPS 25mm x 30kg | $3,545,143.45 | $356,941.90 | $3,902,085.36 | 2.24% |
| 8 | Basecoat y malla de fibra de vidrio | $2,720,224.64 | $273,885.84 | $2,994,109.79 | 1.72% |
| 9 | Instalación de luz | $5,331,819.70 | $2,513,888.84 | 7,845,708.54 | 4.50% |
| 10 | Instalación de agua | $1,296,810.62 | $1,108,433.20 | $2,405,708.54 | 1.38% |
| 11 | Instalación de gas | $1,154,124.71 | $986,474.14 | $2,140,598.85 | 1.23% |
| 12 | Aislaciones (lana de vidrio de 100mm) | $7,049,471.07 | $622,913.87 | $7,672,384.94 | 4.40% |
| 13 | Emplacado Interior de cielo rasos y muros | $8,084,508.89 | $2,491,655.53 | $10,576,164.42 | 6.06% |
| 14 | Aberturas (modena blanco con vidrios 3+3) | $18,435,184.48 | $0.00 | $18,435,184.48 | 10.57% |
| 15 | Pintura Interior | $399,000.20 | $1,551,542.29 | $1,950,542.50 | 1.12% |
| 16 | Revestimiento plástico exterior | $1,367,906.45 | $669,099.75 | $2,037,006.19 | 1.17% |
| 17 | Pisos interiores, veredas y revestimientos de baño y cocina | $11,823,750.50 | $2,018,835.38 | $13,842,585.88 | 7.94% |
| 18 | Otros | $5,167,605.31 | $0.00 | $5,167,605.31 | 2.96% |
| Subtotales | $123,110,678.48 | $51,337,448.38 | $174,448,126.86 | 100.00% | |
| Participación % | 70.57% | 29.43% | |||
| Precio por M2 | $1,070,527.64 | $446,412.59 | $1,516,940.23 | ||
| *Los valores expresados son aproximados | |||||
*Todas las imágenes son ilustrativas.